Strengthening Forest Management for Improved Biodiversity Conservation and Climate Resilience in the Southern Rangelands of Kenya
GEF Project ID: 10292
GEF-7 | Land Degradation, Biodiversity and Climate change Focal Areas | Implemented through NEMA and MoEF | GEF Partner Agency: IUCN
Project start – 24th April 2023
MTR window – 2026
Focal area – Land Degradation (GEF-7)
Executing partners – NEMA
Responsible parties – KARLO, NETFUND, SORALO, ACC
Landscapes – Kajiado; Narok
1. INTRODUCTION
This document sets out the Terms of Reference (ToR) for the IUCN-GEF Midterm Review (MTR) of the full-sized project titled “Strengthening Forest Management for Improved Biodiversity Conservation and Climate Resilience in the Southern Rangelands of Kenya” (Project ID: 10292), implemented through the National Environment Management Authority (NEMA), and to be undertaken in 2026.
The project commenced on 24th April 2023 and is in its third year of implementation. In line with the IUCN-GEF Guidance on MTRs, this MTR process is initiated ahead of the submission of the second Project Implementation Report (PIR). The MTR process must follow the guidance outlined in GEF’s evaluation process: https://www.thegef.org/sites/default/files/documents/2026-05/GEF_EN_Evaluation_Policy_May_1.pdf.
This ToR defines the objective, scope, methodology, deliverables, timeframe, team composition, and management arrangements for the review. It is complemented by the annexes, which set out the documents to be reviewed and the required structure of the MTR report.
2. PROJECT BACKGROUND INFORMATION
2.1 About IUCN
IUCN (International Union for Conservation of Nature) is a membership Union uniquely composed of both government and civil society organisations. It provides public, private, and non-governmental organisations with the knowledge and tools that enable human progress, economic development, and nature conservation to take place together.
Created in 1948, IUCN is now the world’s largest and most diverse environmental network, harnessing the knowledge, resources, and reach of more than 1,400 Member organisations and around 15,000 experts. It is a leading provider of conservation data, assessments, and analysis, and fills the role of incubator and trusted repository of best practices, tools, and international standards.
IUCN provides a neutral space in which diverse stakeholders — governments, NGOs, scientists, businesses, local communities, Indigenous peoples’ organisations, and others — can work together to forge and implement solutions to environmental challenges and achieve sustainable development. Working with many partners and supporters, IUCN implements a large and diverse portfolio of conservation projects worldwide, combining the latest science with the traditional knowledge of local communities to reverse habitat loss, restore ecosystems, and improve people’s well-being.
2.2. Project Development Context
The Southern Rangelands of Kenya, covering large areas of Kajiado and Narok Counties, contain globally significant biodiversity, critical forest ecosystems, wildlife dispersal areas, and pastoral production systems that provide essential ecosystem services, including biodiversity conservation, water regulation, carbon storage, livestock production, and tourism. These landscapes are increasingly threatened by land degradation, forest loss, unsustainable land-use practices, invasive species, climate variability, changing land tenure, habitat fragmentation, and increasing pressure from agricultural expansion, infrastructure development, and competing land uses.
Although Kenya has a relatively strong policy framework for forest management, biodiversity conservation, and sustainable land management, implementation remains constrained by fragmented institutional coordination, inadequate landscape planning, limited financing for restoration, weak community capacity, insufficient knowledge management, and inadequate incentives for sustainable natural resource management.
The GEF-7 project **”**Strengthening Forest Management for Improved Biodiversity Conservation and Climate Resilience in the Southern Rangelands of Kenya” (GEF ID 10292) seeks to address these constraints through an integrated landscape approach combining enabling policies, investments in sustainable dryland management, ecosystem restoration, biodiversity conservation, sustainable livelihoods, knowledge generation, and multi-stakeholder coordination. The project contributes simultaneously to the GEF Land Degradation, Biodiversity, Climate Change, and Sustainable Forest Management Impact Program objectives while supporting Kenya’s national development and environmental commitments.
The Mid-Term Review will assess progress towards these objectives, validate the project’s Theory of Change, examine implementation performance (measurable environmental and socio-economic results), identify emerging opportunities and implementation bottlenecks, and recommend adaptive management actions for the remainder of the implementation period.
2.3 Barriers addressed by the project
The project responds to six interlinked barriers to the uptake and scale-up of in the target landscapes:
Weak integrated landscape governance and cross-sector coordination: Forest, wildlife, rangeland and agricultural planning are undertaken by different institutions with insufficient coordination across sectors and administrative levels.
Limited enabling environment for sustainable forest and dryland management: Existing policies, planning tools and institutional capacities are not sufficiently operationalized to support integrated landscape management.
Insufficient investment in restoration and sustainable natural resource management: Financial resources, incentives and private-sector engagement remain inadequate for large-scale restoration and sustainable land management.
Limited adoption of sustainable land and forest management practices: Communities require greater technical support, demonstration, extension services and access to technologies that improve productivity while conserving biodiversity.
Weak knowledge management, monitoring and evidence-based decision making: Ecological monitoring, landscape information systems and knowledge-sharing mechanisms are insufficient to guide adaptive management and scaling.
Market and livelihood constraints: Pastoralists and other land users have limited opportunities to derive sustainable economic benefits from biodiversity conservation, restoration and sustainable value chains.
2.4 Project components
2.5 Implementation focus
Project implementation focuses on strengthening integrated landscape governance in Kajiado and Narok Counties; improving sustainable forest and dryland management; restoring degraded ecosystems; enhancing biodiversity conservation and climate resilience; promoting sustainable livelihood and value-chain opportunities; strengthening institutional coordination among national and county agencies; supporting community participation in natural resource governance; and establishing robust monitoring, knowledge management, and learning systems. Implementation is led by NEMA, in collaboration with the Ministry responsible for Environment and Forestry and Responsible Parties, including KARLO, NETFUND, SORALO, ACC, and ILRI, and works closely with county governments, community institutions, and other stakeholders.
3. OBJECTIVE OF THE MTR
The purpose of the MTR is to provide an independent, evidence-based assessment of whether the project is on course to achieve its objective and intended outcomes, and to identify the management, technical, institutional and strategic adjustments required to maximise results during the remaining project period. The MTR will assess progress towards achieving the project objective and outcomes as specified in the Project Document, and identify early signs of project success or failure, with the goal of identifying the changes needed to set the project on track to achieve its intended results. The MTR will also review the project’s strategy and its sustainability risks.
The specific objectives are to:
4. MTR APPROACH AND METHODOLOGY
The MTR must provide evidence-based information that is credible, reliable, and useful. The MTR shall adopt a utilization-focused, participatory and mixed-methods evaluation approach, consistent with the GEF Evaluation Policy and IUCN-GEF Mid-Term Review Guidance. The MTR team will review all relevant sources of information, including documents prepared during the preparation phase (e.g., the Project Document and the CEO Endorsement package, the Environmental and Social Screening/safeguards documentation, project reports including Annual Project Review/PIRs, annual workplans project budget revisions, lessons-learned reports, and national strategic and legal documents), together with any other materials the team considers useful.
The review shall combine qualitative and quantitative evidence to assess project performance, validate findings through triangulation and generate practical recommendations for adaptive management. Attention shall be given to assessing both implementation performance and the project’s contribution to intended environmental and socio-economic outcomes. The review will be conducted through a collaborative and participatory approach, drawing on appreciative enquiry to facilitate reflection and learning, and ensuring close engagement with the Project Management Unit, government counterparts (including the GEF Operational Focal Point), the IUCN Kenya Country Office, the IUCN Multilateral Finance Regional Portfolio and Delivery Managers and Regional M&E lead, and other key stakeholders. The review will be structured around the following complementary methods:
The final MTR report must describe the full approach and the rationale for it, making explicit the underlying assumptions, challenges, strengths, and weaknesses of the methods used. The MTR will apply the OECD-DAC evaluation criteria (relevance, coherence, effectiveness, efficiency, sustainability, and where relevant – impact). These criteria are addressed through the four assessment categories set out in the scope of the MTR in Section 5, and are operationalised in detail in the MTR evaluative matrix (Annex B). Consultants are expected to set out their proposed interpretation of this ToR, including their evaluation approach, methodology, and workplan, in their technical proposal at the bid stage. Following award, the appointed consultant will develop this into a consolidated and refined approach, including the finalised methodology, evaluation matrix, sampling, and workplan, in the Inception Report (Deliverable 1). This consolidated approach must be reviewed and signed off by the IUCN M&E Lead before data collection begins, and will serve as the agreed basis against which the MTR is conducted and its deliverables assessed.
5. DETAILED SCOPE OF THE MTR
The MTR team will assess the following four categories of project progress: (i) Project Strategy; (ii) Progress Towards Results; (iii) Project Implementation and Adaptive Management; and (iv) Sustainability. Environmental and social safeguards (ESMS) performance is assessed within category (iii), as set out below. The categories map onto the OECD-DAC criteria as shown in Section 4, and each is operationalised through the evaluative matrix in Annex B.
(i) Project Strategy and relevance
Undertake a critical analysis of the logframe indicators and targets; assess how SMART the mid-term and end-of-project targets are (Specific, Measurable, Attainable, Relevant, Time-bound) and suggest amendments as necessary.
(ii) Progress towards results, outcome harvesting analysis
For each outcome and output indicator, establish the reported current value at mid-term and compare it against three reference points: the baseline, the mid-term milestone (where one exists), and the end-of-project target. Express progress as a percentage of the end target and colour-code it in the Progress Towards Results Matrix (green = on track, amber = at risk, red = off track), assigning a rating on the GEF scale for each outcome.
Component 1 – Strengthening the enabling environment for sustainable management of natural resources in the drylands
The MTR will assess the extent to which Component 1 has strengthened the enabling environment for integrated landscape management and sustainable natural resource management in the Southern Rangelands.
In particular, the review will assess whether:
Component 2 – Investment in Scaling-up Sustainable Dryland Management
The MTR will assess the extent to which Component 2 is delivering effective field-level investments that contribute to sustainable forest management, biodiversity conservation, ecosystem restoration and improved livelihoods.
The review will assess whether:
Component 3 – Programmatic Coordination, Monitoring and Knowledge Management
The MTR will assess the extent to which Component 3 has established effective systems for project coordination, monitoring, learning and adaptive management.
The review will assess whether:
Progress towards impact-Testing the project theory of change-
Progress towards integrated landscape outcomes
iii. Project Implementation and Adaptive Management
Management arrangements
Work planning
Finance and co-finance
Project-level monitoring and evaluation systems
Environmental and Social Safeguards (ESMS) performance
Stakeholder engagement
Reporting
Communications
iv. Sustainability
Financial risks to sustainability
Socio-economic risks to sustainability
Institutional framework and governance risks to sustainability
Environmental risks to sustainability
Human rights and gender equity
6. RATINGS
The MTR team will rate the project’s progress in the Executive Summary using the standard IUCN-GEF scales. Outcomes and project implementation are rated on a six-point scale; sustainability is rated on a four-point likelihood scale reflecting the combined risks. The completed MTR Ratings & Achievement Summary Table must appear in the Executive Summary and be substantiated in the Findings.
Rating Progress Towards Results / Implementation & M&E Meaning
HS – Highly Satisfactory -No shortcomings; targets exceeded or on track to be exceeded.
S – Satisfactory – Minor shortcomings; objectives expected to be achieved.
MS – Moderately Satisfactory – Moderate shortcomings; most objectives expected to be achieved.
MU – Moderately Unsatisfactory – Significant shortcomings; some objectives at risk.
U – Unsatisfactory – Major shortcomings; most objectives unlikely to be achieved.
HU – Highly Unsatisfactory – Severe shortcomings; objectives will not be achieved.
Rating Sustainability Meaning
L – Likely – Negligible risks to sustainability.
ML – Moderately Likely – Moderate risks to sustainability.
MU – Moderately Unlikely – Significant risks to sustainability.
U – Unlikely – Severe risks to sustainability.
7. Ethical use of AI
Consultants may use Artificial Intelligence (AI) tools to support aspects of the evaluation process for instance transcription of interviews, coding of qualitative data and summarizing documents during desk review etc. however consultants will remain fully accountable for the quality, accuracy, confidentiality, integrity, and ethical conduct of the evaluation. AI should not be used to fabricate or misrepresent evidence, analyses, findings, or conclusions. All evaluation findings must be based on verified data collected through the evaluation methodology that the consultant shall agree with IUCN evaluation team. Consultants must ensure that confidential or personally identifiable information is not uploaded to public AI platforms and may be required to disclose how AI was used during the process.
8. MTR TIMEFRAME AND DELIVERABLES
The total duration of the MTR will be approximately 92 calendar days, commencing with the close of applications on 07 August 2026 and concluding with issue of the final MTR report by 07 November 2026. The indicative schedule is set out below; IUCN will confirm exact dates on contracting and will accommodate reasonable delays for the circulation and review of the draft report.
Milestone Activity Indicative timing
Application closes – Deadline for submission of proposals – 21 September 2026
Selection & appointment – Evaluation and appointment of the MTR team – 28 September 2026
Kick off meeting – First engagement with IUCN and handover of project documents to the consultant – 5 October 2026
Submission of inception report – Document review and preparation of the MTR Inception Report (2–4 days) – 9 October 2026
Inception validation – Finalisation and validation of the Inception Report – 16 October 2026
MTR mission – Stakeholder meetings, interviews, and field visits (15 days) – 17-28 October 2026
Wrap-up & initial findings – Mission wrap-up meeting and presentation of initial findings – 2 November 2026
Draft report – Preparation of the draft MTR report (approx. 7 days) – 9 November 2026
IUCN team/ PMU / OFP review – Circulation and review of the draft report – 20 November 2026
Final report – Incorporation of audit trail and issue of the final MTR report – 27 November 2026
# Deliverable Description Timing & responsibility
1.MTR Inception Report – MTR team clarifies objectives, methodology, evaluation matrix, and work plan.
No later than 2 weeks before the MTR mission; submitted by the consultant to the IUCN Country Representative, IUCN Regional M&E lead (approver), IUCN Regional Programme Delivery Manager, IUCN Regional Multilateral Finance lead (henceforth, the IUCN team).
2.Presentation of Initial Findings – Presentation of preliminary findings following the field mission.
End of the MTR mission; presented to the IUCN team, government, and implementing partners.
3.Draft Final Report – Full report using the content guidelines in Annex B, with annexes.
Within 3 weeks of the mission; reviewed by IUCN team, and the GEF OFP.
4.Final Report – Revised report with an audit trail detailing how all comments have (and have not) been addressed.
Within 1 week of receiving IUCN comments; submitted to the IUCN team for approval.
5.Datasets – Provide transcripts of all qualitative data used and clean quantitative datasets used during the evaluation data collection
Submit this together with the final report
6.Evaluation Brief – A 3–5-page summary of the evaluation findings and recommendations.
Submit this together with the final report
9. PAYMENT SCHEDULE
The table below summarises the milestones at which IUCN will pay the consultant. Payments are made against the approval of each deliverable and sum to 100% of the contract value.
Milestone % of fee Cumulative
Approval of the Inception Report – 20% – 20%
Completion of the field mission and presentation of initial findings – 30% – 50%
Submission of the Draft Final Report – 30% – 80%
Submission and approval of the Final Report (with audit trail) – 20% – 100%
Total – 100%
10. MTR ARRANGEMENTS
Principal responsibility for managing this MTR resides with the IUCN M&E Lead, working together with the IUCN Regional Portfolio Manager, who jointly form the commissioning function for this review. The M&E Lead holds overall responsibility for the quality and independence of the process and for formal sign-off of the MTR deliverables, while the Regional Portfolio Manager ensures alignment with GEF requirements and project oversight. The IUCN Kenya Country Office will support the consultants in engaging government partners and will provide logistical support for the consultations, including the timely provision of per diems and travel arrangements within Kenya for the MTR team, comprising the appointed consultants and, where required, regional IUCN staff. The Project Management Unit (PMU) will act as the primary operational point of contact for the MTR team: providing all relevant project documents, setting up stakeholder interviews, arranging field visits, and facilitating access to data and records. To preserve the independence of the review, the PMU’s role is limited to facilitation and information provision; it holds no authority over the findings, ratings, or recommendations of the MTR.
11. TEAM COMPOSITION
The MTR will be conducted by a two-person team working under a single contract arising from these Terms of Reference: an international Lead Consultant and a national/local expert based in Kenya. The team members should not have participated in the project’s preparation, formulation, or implementation (including the writing of the Project Document) and must not have any conflict of interest with the project’s activities. Each team member will be required to sign the IUCN Code of Conduct and a conflict-of-interest declaration prior to commencement.
11.1 Lead Consultant (International)
The Lead Consultant holds overall responsibility for the design and delivery of the MTR, the quality of the methodology, and the final report. Indicative responsibilities include: review and analysis of project reports; reflection on the appropriateness of the original design and approaches; consideration of project methodologies in relation to policy; engagement of partners and key stakeholders; reflection on the expected impact pathway; and identification of approaches with future implications.
11.2 National / Local Expert (South Kenya)
The National Expert provides in-country and technical grounding for the review, including analysis of project context and progress over the lifespan of execution; facilitation of and support to stakeholder engagement and field logistics; identification of key lessons learned; and contribution to the overall findings and recommendations. The National Expert supports the Lead Consultant in finalising the report and addressing review comments.
11.3 Required qualifications and evaluation criteria
The team, collectively, should demonstrate the following. Points indicate the weighting applied when scoring the technical proposal (total: 100 points).
Evaluation Criterion Specific requirements Weighting
Evaluation team composition – 20%
Experience relevant to the terms of reference – 15%
Independence – 5%
Understanding of the terms of reference – 20%
Evaluation methodology – 25%
Evaluation work plan – 15%
12. APPLICATION PROCESS
Interested candidates should submit the following:
Proposals will be assessed using a Quality- and Cost-Based Selection (QCBS) method. The technical proposal accounts for 70% and the financial proposal for 30% of the total score; only proposals scoring at least 70% on the technical evaluation will proceed to financial assessment. Please refer to the Request for Proposals document for further information.
Annex A. DOCUMENTS TO BE REVIEWED BY THE MTR TEAM
The following documents will be provided to the MTR team:
The following documents will also be available:
Annex B. CONTENT OUTLINE FOR THE MIDTERM REVIEW REPORT
The MTR report shall follow the structure below. Indicative page lengths are guidance, not limits. Every finding must be evidence-based and, where a rating applies, substantiated in the body.
Basic Report Information (title page)
Table of Contents · Acronyms and Abbreviations
Executive Summary (3–5 pages)
1. Introduction (2–3 pages)
2. Project Description and Development Context (3–5 pages)
3. Findings (12–14 pages)
3.1 Project Strategy
3.2 Progress Towards Results
3.3 Environmental and Social Safeguards (ESMS) Performance
3.4 Project Implementation and Adaptive Management
3.5 Sustainability
4. Conclusions and Recommendations (4–6 pages)
Annexes to the Report
Tagged as: International Union for Conservation of Nature, Kenya
You will play a critical role at the intersection of Financial Planning & Analysis (FP&A), accounting, fundraising, and program delivery....
Apply For This JobTerms of reference for IUCN Consultancy Title: Consultancy for Monitoring and Implementation Support for Institutional Strengthening of Community Rangeland Governance...
Apply For This JobAbout One Acre Fund Founded in 2006, One Acre Fund equips 5.5 million smallholder farmers to make their farms more...
Apply For This JobStarting position: 1.11.2026 Type of contract: National contract in accordance with Kenyan labour legislation Duration : 12 months Rate of...
Apply For This JobAbout the Project The African Academy of Sciences (AAS) is partnering with the Frontiers Research Foundation (FRF) to promote the...
Apply For This JobBACKGROUND ON IMPACT Created in 2010, IMPACT is a Geneva-based NGO and the largest independent data provider in contexts of...
Apply For This Job